WAC 296-46B-590 Temporary installations.

Click to Enlarge

WAC 296-46B-590 Temporary installations.

001 Temporary installations.

(1) For the purposes of this section, any circuit used for construction purposes is considered to be temporary.

003 Temporary installations – time constraints

(2) Temporary construction service equipment may only be used for construction purposes and must be disconnected when the permanent service is connected unless the department grants an extension of time.

004 Temporary installations - splices.

(3) A splice or junction box is required for all wiring splice or junction connections in a temporary installation.

  Click here to review the Washington Administrative Code  

Did You Like This? Let Us Know With A Like! Thanks!

WAC 296-46B-590 Temporary installations.

Below is a Real Question from our Electrical Continuing Education Courses for Electrical License Renewal:

In Washington, which of the following is true for construction power?

A: Circuits used for construction purposes are considered to be permanent.
B: Temporary construction service equipment must be disconnected when the permanent service is connected unless the department grants an extension of time.
C: Temporary construction service equipment may be used for other than construction purposes.
D: Splices and junction boxes are not required for temporary installations.