RCW 19.28.331 Inspection reports.

Click to Enlarge

19.28.331 Inspection reports.

If any inspection made under this chapter requires any correction or change in the work inspected, a written report of the inspection shall be made by the inspector, in which report the corrections or changes required shall be plainly stated. A copy of the report shall be furnished to the person, firm, partnership, corporation, or other entity doing the installation work, and a copy shall be filed with the department.

  Click here to review the Revised Code of Washington  

Did You Like This? Let Us Know With A Like! Thanks!

RCW 19.28.331 Inspection reports.

Below is a Real Question from our Electrical Continuing Education Courses for Electrical License Renewal:

In Washington, which of the following is true regarding a failed inspection?

A: Corrections required by the inspector must be completed within 48 hours.
B: Corrections required by the inspector must be completed within 24 hours.
C: A written report of the inspection shall be made by the inspector, in which report the corrections or changes required shall be plainly stated.
D: A verbal report of the inspection shall be made by the inspector.