NEC Section 230.82 specifies all things permitted to be installed on the line side or ahead of the service disconnect. This is a dangerous location since no overcurrent protection is present ahead of the service disconnect. One of the items permitted is a meter disconnect switch.
Many utility companies require a meter disconnect switch so that the load on an electrical service can be dropped before changing or removing the electric meter. Quite often, the utility company pulls the electric meter when the building occupant fails to pay the electricity bill.
Meters are not generally designed to be pulled under load which is why a load break rated meter disconnect switch is used ahead of the meter. In order to comply with the rule in 230.82(3), the meter disconnect switch must have a short-circuit current rating (SCCR) equal to or greater than the available short-circuit current also known as the Available Fault Current (AFC).
See the actual NEC® text at NFPA.ORG for the complete code section. Once there, click on the “free access” tab and select the applicable year of NFPA 70 (National Electrical code).
2020-2023 Code Language:
230.82 Equipment Connected to the Supply Side of Service Disconnect.
(3) Meter disconnect switches nominally rated not in excess of 1000 volts that have a short-circuit current rating equal to or greater than the available fault current….
2026 Code Language:
230.82 Equipment Connected to the Supply Side of Service Disconnect.
(3) Meter disconnect switches that comply with the all of the following:
a. Have a short-circuit current rating equal to or greater than the available fault current
b. See the actual NEC…
c. See the actual NEC…
Refer to the image.
How is the SCCR of the fused disconnect switch changed when different fuses are installed?
| Please register or sign in for electrical continuing education courses. If you were already signed in, your session probably expired, please sign back in. |