918-309-0050 Permits for the Temporary Service or Temporary Feeder. These rules are located here: Oregon Administrative Rules
(1) Permit for each temporary construction service or temporary feeder for light and power:
(a) 200 amps or less, $63;
(b) 201 amps to 400 amps, $86;
(c) 401 to 600 amps, $125;
(d) Temporary service or temporary feeder of over 600 volts or amps use fee schedule in OAR 918-309-0040(4), (5) and (6).
(2) OAR 918-309-0040(7) to (12) are applicable.
(3) The fee used in this section includes the branch circuits.
What is the permit fee for a single, 240-volt, 400 amp temporary electrical service for the purpose of jobsite power during construction?