Miscellaneous Permit Fees.

Click to Enlarge

918-309-0070 Miscellaneous. These rules are located here: Oregon Administrative Rules

(11) Permit fees for renewable electrical energy systems. For renewable electrical energy permit applications, see OAR 918-309-0410. For repairs and maintenance of renewable electrical energy systems, see OAR 918-309-0220(5).

(a)

(A) 5 KVA or less: $79;

(B) 5.01 KVA to 15 KVA: $94;

(C) 15.01 KVA to 25 KVA: $156.

(b) For wind generation systems in excess of 25KVA:

(A) 25.01 KVA to 50 KVA: $204;

(B) 50.10 KVA to 100 KVA: $469;

(C) For wind generation systems that exceed 100 KVA the permit fee is calculated in accordance with OAR 918-309-0040.

(c) For solar generation systems in excess of 25KVA:

(A) Each additional KVA over 25 will be charged an additional $6.25 per KVA.

(B) The permit charge will not increase beyond the calculation for 100 KVA.

(d) Permits issued under this sub-section include three inspections. Additional inspections will be billed at an hourly rate.

Did You Like This? Follow us on Face Book! Thanks!

Electrical License Renewal Facebook Logo

Miscellaneous Permit Fees.

Below is a Real Question from our Electrical Continuing Education Courses for Electrical License Renewal:

What is the permit fee for a 30 KVA, ground mounted solar photovoltaic system?

A: $187.25.
B: $156.
C: $180.50.
D: $204.